22 October 2001 - Work began with protective fencing being put into place |
The old chain link fencing |
Once the chain link fencing was removed trial holes were dug to see what the ground was like below the surface. |
The contractors were ready to start work on demolishing the brick gateway. |
The brick gateway was demolished... |
and, with a lot of noise(!), |
Trenches to take the foundations of the new wall were dug along the edge of the school site. |
As the earth was removed, it was piled on boarding to protect the tarmac. |
Later, lorries came to remove the earth from the school site. |
Even before the foundations were laid the bricks for the wall arrived. |
The lorry returned ... |
to take away the material |
To get ready for putting in the foundations, deliveries of cement ... |
sand & aggregate - and sheets of polystyrene arrived. |