For
a number of years the school roof had been leaking in a number of
different places and cracks had been appearing in the walls. The
school had sought advice and several attempts had been made to sort out
the problems. By 2005 it was was realised that the only way
forward was a major overhaul of the roof. A national roofing
consultant was commissioned to carry out a survey and produce a
report. Armed with this the school asked for a large Capital grant
to carry out major works. After much effort sufficient funding was
secured to deal with two thirds of the building, covering all those
areas where there were significant problems. |
|
|
|
Mr. Rutter was a little alarmed to find that the chute to remove material from the roof directly into the skip was right outside his window. |
|
|
|
To ensure that the new roof met modern standards, special insulation material was used. |
As works progressed it was possible to see just how bad the roof had become. |
|
|
The
coping stones along the top of the wall were removed and replace with |
This was later covered with high quality roofing material. |
|
|
By
early August the works were |
although there was still a long way to go. |
|
|
Fortunately
up to that point |
Because a thick layer of insulation was being added, the doorway onto the roof had to be raised. |
|
|
Also, the thin, high windows in the |
Year 5 classrooms had to be removed |
|
|
and bricked up. |
The insulation could then be added |
|
|
and covered. Flame torches were used... |
to melt the tar that would bind all the materials and make them waterproof. |
|
|
As this section of the work neared completion... |
we
could see how well the building |
|
|
Another task the roofers did was to ... |
replace the skylights. |
|
|
As we got into September ... |
and the start of the term... |
|
|
the
work drew to a close and we knew the school... |
would
be water tight for many years |
First uploaded: 28 October 2006
Last updated: 19 December 2018