The path was ready |
The posts and handrails |
The upright posts |
All the posts were in place ready |
Tarmac was unloaded |
The handrails are all in place |
In the week beginning 4 February |
... the great day was early morning on the 6 February when the fencing and gates arrived. |
Within an hour or so the first part of the fencing was fitted into place. |
The gate to the new junior path |
The main gate took a little more time to make sure the two sides matched exactly. |
For the first time it was possible to see how good the finished boundary wall would look. |
Under the entrance to the school the mains water pipe had a small leak. |
So a trench was dug |